Residensi Hijauan Pantai: July 2025 – Latest Progress & Buyer Action

Despite visible structural progress, Residensi Hijauan Pantai (RHP) buyers are growing restless. The superstructure has topped out at Level 50, but livability and compliance remain in serious question. Infrastructure, CCC issuance, and internal works lag far behind, with multiple buyers organizing legal and public pressure in response.

What’s Done & What’s Delayed

  • Level 50 structure completed (main tower topped out)
  • ⚠️ Internal works incomplete: window fittings, wall plaster, toilets
  • ⚠️ Car park podium & facilities still at <20% progress
  • Utilities (water, electricity, drainage, lighting) remain untouched
  • CCC (Certificate of Completion & Compliance) not in sight

Buyer Frustrations Intensify

  • Disputes over developer’s claim of “200 workers on-site”
  • Lack of consistent updates, vague handover timelines
  • Buyers with bank loans (e.g. Maybank) already incurring progressive interest
  • No firm CCC or VP (Vacant Possession) date from Impero Land
  • Concerns that delays could violate the SPA timeline and limit LAD claims

Legal Strike Room: What Buyers Are Doing Now

  • Preparing SPA-based LAD claim templates for all 629 buyers
  • Exploring collective legal representation from strata specialists
  • Drafting press releases for The Star, Malay Mail, and online media
  • Gathering support to submit a formal memorandum to KPKT/DBKL
  • Coordinating data collection via spreadsheets and group leadership roles

Next Milestone: August 2025

Buyers are watching August closely. If Impero Land fails to show real progress, especially on CCC, car park podium, and infrastructure, several groups are prepared to escalate to legal action, public campaigns, and direct federal complaints.